Owner: Expedition Water Service – EWS #6

Location: Firestone, CO

Completion Date: July 2019

Project Scope:

This is the largest water injection facility Expedition has built to date and the fifth facility we’ve built for them. This new disposal plant gives them the ability to take 10,000 barrels a day. Our crews installed the electrical system for (3) 500hp pumps, (24) system tanks, and (5) oil tanks and the motor control center we installed gives them the electrical capacity to expand. The project required 5,000 feet of underground conduit and in addition to all the work in the tank farm, we performed the tenant finish for their 8,000 square foot pump house/office building.